Polski English Informator dla Inwestorów Infomator dla Samorządów Agencja Rozwoju Aglomeracji Wrocławskiej
  • Menu:
  • Aktualności
  • Informacje ogólne
  • Cele spółki
  • Akcjonariat
  • Rada programowa
  • Rada nadzorcza
  • Zarząd
  • Struktura organizacyjna
  • Projekty i zadania
  • Oferta
  • Referencje
  • Listy intencyjne
  • Ogłoszenia i przetargi
  • Oferty pracy
Wyszukiwarka Terenów Inwestycyjnych Raport Driven by knowlege Wrocław Europejska Stolica Kultury - Kandydat
Strona Główna > News > News > The stadium is expanding
The stadium is expanding
Wrocław stadium for Euro 2012 is growing bigger and bigger every day. Giant bolts, over one hundred tones each, were placed in the site at the end of August. There will be fifty of them in all. First football games in the new stadium are planned for summer of 2011.

Biggest bolts weigh 110 tones each

fot. Wrocław 2012 sp. z o.o.

Six biggest bolts were installed first. Each of them is 36 metres high and weighs 110 tones including 40 tones of armature. In the end, fifty such bolts will prop the tribunes in the corners of the stadium.

Earlier, in the second half of August, the making of the ceiling over L-2 level was finished and first ceilings over L-3 level were filled with concrete. First pillars at the level L-4 were placed on the ceilings finished, and these pillars prop the bolts.

Detailed agenda of construction works in the stadium:

Main tribune:
•    Bolts: April 2010 – August 2010
•    Steps: July 2010 – September 2010

Northern curve:
•    Tribune bolts: April 2010 – September 2010
•    Tribune steps: August 2010 – September 2010

Opposite tribune:
•    Tribune bolts: May 2010 – June 2010
•    Tribune steps: September 2010 – October 2010

fot. Wrocław 2012 sp. z o.o.

Southern curve:
•    Tribune bolts: June 2010 – November 2010
•    Tribune steps: September 2010 – December 2010

Steel construction:
•    Installation of the steel construction of the roof: August 2010 – April 2011
•    Façade and roofing: October 2010 – April 2011
•    Installation of glad elements: December 2010 – April 2011
•    Installation of the diaphragm: January 2011 – April 2011
•    Installation of chairs: September 2010 – March 2011

The pitch:

•    Laying the lawn: May 2011 – June 2011
•    Grass growth: June 2011
•    Esplanade: January 2011 – June 2011
•    Multi-level car park: June 2010 – April 2011

Warm-up of the stadium: July 2011 – October 2011


Aktualności | Informacje ogólne | Cele spółki | Akcjonariat | Rada programowa | Rada nadzorcza | Zarząd | Struktura organizacyjna | Projekty i zadania | Oferta | Referencje | Listy intencyjne | Ogłoszenia i przetargi | Oferty pracy | Oferta ARAW | Komunikacja | Zainwestowali | Pomoc publiczna | Do ściągnięcia | Partnerzy | Kontakt | Oferta dla Akcjonariuszy | Oferta dla pozostałych JST | Podmiot wewnętrzny | Zamówienia wspólne | Partnerstwo Publiczno Prywatne | Zielone zamówienia | Pozyskiwanie Finansowania | Zarządzanie i planowanie | Gospodarka odpadami
Lama Media budowa serwisu
Agencja Interaktywna